Hawkley: Village Hall Upgrade

 

Hawkley Village Hall Upgrade Project.

To see photos of the opening party please click here.

For village hall booking information please click here.

 

Plans:

To add changing rooms, showers, disabled toilets, store room, new kitchen, veranda with pitched roof, new entrance, improve flooring, decoration and lighting.

To see a provisional floor plan please click here.

Cost:

We anticipate the cost of the project to be £250,000

 

Progress report:

The hall was cleared by villagers and cricketers during december.

clear out

After an initial slow wet start building work is now underway. The building is now re- arranged internally with new kitchen.

internal 3

Bar ceiling to come off and be replaced with vaulted roof.

internal1

Opening now constructed between Hall and Bar.

internal 4 internal 2

The extension to house the changing rooms/showers and toilets has come out of the ground.

external 1 external 2

Storeroom will be added

storeroom1

Roof construction starting (28/01/2011)

roof 1 roof 2

roof 3

You can see the internal vaulted roof developing in the bar

internal roof

Oak arrives by lorry just in time

crane

Internal beams are constructed and looking good!

beams 1 beams 2

 

Now the whole length of the hall has a roof on it.

whole roof

 

For more information please contact :

Nick Davis 01730-827507

 

 

 

© nick davis 2009